Friday, April 3, 2009

Day 5

Morning
Went across the street to S8 and started taking down notes. We looked at the panel with the Kepco and the PLC box to determine which inputs and outputs were controlling the guns. The real problem was that some wires were labeled with "lateral" and "radial", but then they change to "x" and "y" on the other side of the room. I should have all of the correct labels, but it can be unnerving.

Afternoon
Got to work in AutoCAD drawing up all the wires. Found that I hadn't forgot all of the time I'd spent working with CAD. I used some old drawings as a starter to draw a clean diagram for the wiring of the inputs and outputs. These should come in handy later when I have to read the program.

No comments: