Monday, June 1, 2009

Day 46

Morning
I worked in the office during the morning. Starting by layout the I/O for EBW 1 and 5, I was trying to get some more work done on the welder upgrade. I began drafting a desired theory of operation document. It will outline what the system needs to do and in what order. From there I can write up the new program in RS Logix 5000.

Afternoon
Working with Tony on getting the fixes for EBW 4 going. We grabbed a different trigger board from S7 and some diodes from the instrument shop before trying to fire the bombardment again. It worked pretty well until the small transformer blew. It threw a pretty large puff of white smoke. We should get a new trigger board from Owen before long.