Morning
Ladd doesn't need the brake system that I designed. They are going to use a 120V coil. I finished up my drawings today. They helped me find a few things that I missed. The D.P. heat relay's weren't on the I/O, so I added them in. Once the drawings for the I/O was all done I wrote up a bill of materials and emailed it to North Coast for a price quote. Tony was having some strange issues on 4 EBW at around 11:00, so I watched the troubleshoot. It might have been a fluke thing, but we never did find the cause.
Afternoon
After helping Chris take a picture of a copper spot, I started to lay out the budget worksheet for the welder project. It has different sections for upgrading welders, putting them on the network, and for getting trending going. The difficult part for me is that I barely know what we need for parts, much less all the labor to install this stuff. I got started with all of the things I think we need, then I started estimating labor costs.